10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
These 10 free LAW questions are organized by exam domain, so you can see how each part of the California Contractors Law and Business Exam blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Business Organization and Licensing 13% of exam
Question 1
A homeowner asks an unlicensed individual to replace several fence boards as a casual, minor repair for a total price of $880, including labor and materials. No permit is required, the individual will work alone, the job is not part of a larger project, and the advertisement states "Not a licensed contractor." Under California contractor licensing law, the licensing result is:
Show answer & explanation
Correct answer: C - The work may qualify for the minor-work exemption because every stated condition is met
Question 2
A general contractor offers a Class B licensee a tile-only subcontract. The Class B firm does not hold a C-54 tile classification and plans to pass the entire scope to a licensed C-54 subcontractor. Which response is legally sound?
Show answer & explanation
Correct answer: A - Decline the tile-only subcontract unless it first obtains the C-54 classification
Domain 2: Business Finances 15% of exam
Question 3
At a growing contracting company, one accounts-payable employee can create vendors, approve invoices, release ACH payments, and reconcile the bank account. Select the control that most directly breaks this fraud opportunity.
Show answer & explanation
Correct answer: B - Assign vendor setup, payment approval, and bank reconciliation to different people
Question 4
An estimator expects a job to cost $240,000, and management requires a 20% gross margin on the selling price. Ignoring tax and financing effects, determine the bid that meets the requirement.
Show answer & explanation
Correct answer: D - $300,000
Question 5
Before mobilization, a customer pays a $50,000 deposit for work the contractor has not yet earned. What should the initial entry recognize?
Show answer & explanation
Correct answer: A - Increase cash and increase a liability
Domain 3: Employment Requirements 20% of exam
Question 6
Applying California's ABC test, a roofing company issues a 1099 to a worker who installs roofs, which is the service the company sells. The company sets the worker's schedule and methods, and the worker has no separate roofing clients or independently marketed business. How should the worker be classified under that test?
Show answer & explanation
Correct answer: B - Employee, because the company cannot satisfy all three parts of the ABC test
Question 7
An eight-employee contractor wants to screen conviction history for a project-manager applicant. Identify the compliant hiring sequence.
Show answer & explanation
Correct answer: D - Make a conditional offer, assess job relevance, give preliminary notice, and allow at least five business days
Question 8
During a shutdown, a nonexempt employee earns $30 per hour and works 13 hours in one workday. The employee works no other hours that week and has no alternative workweek schedule. Calculate the gross wages due for the day.
Show answer & explanation
Correct answer: C - $480
Question 9
A carpenter quits at 10:00 a.m. Tuesday without giving 72 hours' notice. At separation, the employee has unpaid regular wages, 12 hours of earned vacation, and 24 hours of unused statutory paid sick leave. Which composition and timing of final pay are required?
Show answer & explanation
Correct answer: A - Pay wages and earned vacation within 72 hours; sick leave need not be paid out
Domain 4: Insurance and Liens 12% of exam
Question 10
An employee reports a work-related hand laceration and receives stitches at an occupational clinic. There is no inpatient hospitalization, amputation, eye loss, permanent disfigurement, or time lost beyond the injury date. Select the accurate statement about the DWC-1, Form 5020, and eight-hour Cal/OSHA report.
Show answer & explanation
Correct answer: B - Provide DWC-1 within one working day and send Form 5020 generally within five days; these facts do not trigger the eight-hour report